Project: Courts Unicomer Warehouse

Date: July 2020

Location: Friar's Hill, Antigua

Tests Performed: CPTs | Test Pit Logging

Description:

GID performed a ground investigation at the site of a new warehouse and store facility at Unicomer's Friar's Hill site in Antigua. We mobilised the Modular Matt for a 7-day on-site investigation comprising 6 CPTs along with logging 6 test pits. Site access and navigation was easy, as the flat site had been cleared of all vegetation prior to commencing the investigation.

Each CPT was carried out with attendant pore water pressure measurement to at least 10m per client request. Dissipation tests were also conducted to determine the static piezometric level at each test sounding location.